Clinical trial sites needed calculator: how many sites to hit your enrolment window?

Enter the number of completers you need, the months you have to enrol, what one site recruits at full speed, how fast sites open, and your screen-failure and dropout rates. Get the number of sites, a month-by-month activation schedule and a version of the answer for a slower per-site rate.

  • Funnel back to consent
  • Month-by-month schedule
  • Rate sensitivity
  • Nothing stored

Free sandbox · No credit card · 21 CFR Part 11 compliant

  • ISO 27001 certified
  • 21 CFR Part 11 compliant
  • GDPR compliant
  • EU and US data hosting
  • HIPAA compliant
  • ICH GCP E6(R3) compliant
Demo plan · 120 completers in 18 months, 2 sites open per month

To consent

179

Sites needed

11

If rate −30%

17

If rate −50%

Not reachable

Rate as planned (1.2 per site per month)11/20

11 sites

Rate 15% lower13/20

13 sites

Rate 30% lower17/20

17 sites

Demo numbers. Replace them with your own feasibility data.

Choosing a site count in brief

  • Work backwards first. Completers wanted ÷ (1 − dropout) is the number to randomise, and that ÷ (1 − screen failure) is the number to consent. In the demo, 120 completers means 179 consented participants.
  • Sites are not all open on day one. If two sites open per month and each ramps up over two months, the first months contribute little. The tool adds up each site from its own opening date.
  • The per-site rate is the weakest number in the plan. At 30% below plan the demo needs 17 sites instead of 11, and at 50% below plan no number of sites reaches the target in 18 months at this activation pace.
  • Sites that open after the window ends add nothing. More sites only help while you can still open them, so activation pace and window length limit how far you can compensate for a slow rate.
  • This is the inverse of the enrollment forecast calculator: that tool takes the sites you have and returns a date, this one takes the date you need and returns the sites. Use both to check each other.

Free tool

How many sites do you need?

The example loads a 120-completer trial with an 18-month window. Change any input and the answer, the sensitivity table and the monthly schedule update. Nothing is saved or sent.

%

After randomisation

%

Of those consented

months

Consented participants per site per month

0 = every site open from month 0

months

Linear from 0 to full rate

Sites needed
11
to consent 179 in 18 months
Completers wanted
120
÷ (1 − dropout) → randomise
134
÷ (1 − screen failure) → consent
179
Sites if all opened at month 0
9

With 11 sites opening 2 per month, the expected total at the end of month 18 is 191.4 consented.

What if the per-site rate is lower?

Sensitivity of sites needed to the per-site rate
RateSites neededYour 11 sites would give
100% (1.20)11129 completers
85% (1.02)13110 completers
70% (0.84)1790 completers
50% (0.60)not reachable65 completers

Activation schedule and expected enrolment, month by month (11 sites)

Month-by-month activation and expected enrolment
MonthSites openedSites openConsented this monthCumulative consentedCumulative completers
122
0.4
0.40.3
224
1.9
2.31.5
326
4.2
6.54.4
428
6.6
13.18.8
5210
9.0
22.114.9
6111
11.3
33.422.5
7011
12.8
46.231.2
8011
13.2
59.440.1
9011
13.2
72.649.0
10011
13.2
85.857.9
11011
13.2
99.066.8
12011
13.2
112.275.7
13011
13.2
125.484.6
14011
13.2
138.693.6
15011
13.2
151.8102.5
16011
13.2
165.0111.4
17011
13.2
178.2120.3
18011
13.2
191.4129.2

Planning aid, not a promise: expected values from a smooth model (sites open at even intervals, each ramps linearly to its full rate). Real sites vary, so treat the answer as a minimum and add contingency. Runs in your browser; nothing is stored or sent.

The method

How the site count is calculated, step by step

Step 1, the funnel. Suppose the protocol needs 120 participants to complete. With 10% dropout you must randomise 120 ÷ 0.90 = 133.3, so 134. With 25% screen failure you must consent 134 ÷ 0.75 = 178.7, so 179. These are the same two divisions as in the enrollment forecast calculator, so a plan made in one tool agrees with the other. If your dropout figure is a planning guess, the dropout-adjusted sample size calculator shows how it feeds the statistical section of the protocol.

Step 2, when each site opens. If you open two sites per month, site 1 opens at month 0, site 2 half a month later, site 3 a month later, and so on, evenly spaced at one over the pace in months. Setting the pace to 0 means every site is open from the start, the best case and the answer a feasibility spreadsheet usually gives. The difference between the two answers is the cost of staggered activation: in the demo, 9 sites if all open together against 11 at two per month and 15 at one per month.

Step 3, the ramp-up. A newly opened site needs staff trained, its first consents and a rhythm. The tool ramps each site linearly from zero to its full rate over the ramp-up months. A site that has been open for T months, with a ramp of R months and a full rate r per month, has recruited r × T²/(2R) if T ≤ R, and r × (R/2 + T − R) after that. Add this up for every site that opens before the window closes.

Step 4, the smallest site count that reaches the target. The tool tries 1 site, 2 sites and so on, until the expected total consented reaches the number from step 1. Because sites open one after another, a late site contributes only for the months it is open, so adding site 40 to a 12-month window helps far less than adding site 4.

Checking the tool by hand

One site, open all 12 months, no ramp and a rate of 1 consented participant per month gives 12. Three sites that open one per month, no ramp, a rate of 2 and a 6-month window give 2 × (6 + 5 + 4) = 30. Two sites opening one per month with a two-month ramp, a rate of 1 and a 6-month window give (1 + 4) + (1 + 3) = 9: the first site is open 6 months and the second 5, and each loses half the ramp length. The tool returns exactly 12, 30 and 9 for those inputs, which is a quick test for any enrolment spreadsheet you build yourself.

What moves the site count

Sensitivity: one assumption at a time

Demo plan: 120 completers, 10% dropout, 25% screen failure, 18-month window, 1.2 consented per site per month, two sites opened per month, two-month ramp. Only the listed assumption changes.

ChangeTo consentSites needed
Plan as entered17911
All sites open at month 01799
One site opened per month17915
Three or four sites opened per month17910
Per-site rate 0.84 (30% lower)17917
Per-site rate 0.60 (50% lower)179Not reachable
Screen failure 15%1589
Screen failure 35%20713
Screen failure 45%24416
Window 12 months179Not reachable
Window 15 months17914
Window 24 months1797
Ramp-up 0 months17910
Ramp-up 4 months17912

Model output from the tool above. "Not reachable" means that even opening every site the pace allows inside the window does not produce enough participants.

Defensible inputs

Where the per-site rate and activation pace should come from

Per-site rate. Feasibility questionnaires tend to be optimistic. A better anchor is the registry record of a comparable completed trial: divide its enrolment by its number of sites and by the months between first and last participant in. Count consented participants per open site per month, not eligible patients seen: a site that sees four eligible patients a month and consents a quarter of them is at 1.0. The clinical trial pre-screening tools page covers how earlier screening protects that figure, and the recruitment plan template is where the assumption should be written down.

Activation pace. Use the dates by which contracts, ethics or IRB approvals and drug supply will realistically allow a first consent, not the date a plan hopes for. If the first five sites open together and the rest follow at a steady trickle, enter the slower trickle as the pace and treat the first five as a bonus, or run the tool twice and compare.

Screen failure and dropout. Take them from your own pre-screening log or a pilot where you can, and count them at the same point as the target. A trial with a long run-in fails more people after consent than one with a simple checklist. The screening and enrolment log template records the reasons by site so the rate can be measured rather than guessed.

Contingency. The tool returns the minimum number of sites for the expected enrolment. Real sites vary, and some never recruit. Many teams select more sites than the minimum and plan to close the weakest ones. The sensitivity rows show how much margin each additional percentage point of rate shortfall costs, which helps size that margin.

Where each input comes from
InputBest sourceWeak source
Per-site rateComparable completed trial; your own site logSite self-estimate on a survey
Activation paceContract and approval status per siteThe planned timeline
Screen failurePre-screening log or pilotA rule of thumb from another indication
DropoutSame endpoint, same follow-up lengthAny trial with shorter follow-up
Demo comparison for orientation

Turn the site plan into a working study

Set up your sites, QR enrolment links and visit schedule in the free sandbox and test the flow before the first participant. No credit card.

Start building your study free

In Capture

Running the sites you planned

A site count is only useful if the sites can enrol on day one. Capture is built for multi-site studies, and the enrolment mechanics are the same whether you open three sites or thirty.

  • QR-code enrolment, site-specific or study-specific, with no app install for the participant.
  • Site-level participant numbering (for example 001-0042) and a separate site coordinator portal.
  • By-site data filtering and exports, so you can compare each site with the rate you assumed.
QR code participant enrollment
Study landing page

Now recruiting

Sleep and Recovery Study

A 12-week study of sleep quality after surgery. Takes 5 minutes a day on your phone.

Check if you can take part
12 weeks5 min a dayNo app needed

Scan to join

Print it on posters and clinic flyers

Before you commit

Checks on a site-count plan

Rate counted at the same point as the target

Per-site rate means consented per site per month. If your source counts randomised, convert it first.

A slow-rate case is written down

Run the tool at 70% of the planned rate and keep the answer next to the base case.

Activation pace is evidenced

Each site in the count has a contract and approval route with a realistic date.

The window includes ramp-up

Do not count a site as at full speed in its first one or two months.

A cut-off for weak sites

Decide in advance how many months of low enrolment trigger a replacement or closure.

The timeline agrees

Check the window against the clinical trial timeline calculator so start-up and close-out are not squeezed.

FAQ

Questions teams ask before they switch

Something not covered here? Ask us directly.

How many sites do I need for a clinical trial?

It depends on the number of participants to consent, the months available, what each site recruits per month and how quickly sites open. Convert completers to consented participants first, then find the smallest number of sites whose expected enrolment reaches that total in the window. The calculator above does both steps.

How do I calculate the number of sites from a recruitment rate?

Divide the participants to consent by the rate per site per month and by the months each site is open. For example, 179 consented participants at 1.2 per site per month over 18 months needs about 8.3 sites if every site is open for the whole window. Staggered opening and ramp-up raise that, which is why the demo answer is 11.

Should the per-site rate be randomised or consented participants?

Use the same point as your target in the funnel. This tool uses consented participants per site per month because screen failure sits between consent and randomisation. If your source figure counts randomised participants, divide it by (1 − screen failure) before you enter it.

What happens if my recruitment rate is lower than planned?

You need more sites or more time. The sensitivity table shows both: in the demo a 30% lower rate raises the answer from 11 to 17 sites, and a 50% lower rate cannot be rescued by sites alone inside 18 months at two openings per month. A second lever is a longer window, and a third is a lower screen-failure rate.

How is this different from the enrollment forecast calculator?

The enrollment forecast calculator starts from a number of sites and returns a last-patient-in date with slow, base and fast cases. This calculator starts from the window and returns the number of sites and an activation schedule. They share the same funnel and the same site ramp idea, but the timing model differs in detail, so expect similar rather than identical numbers.

Does the calculator include sites that never recruit?

No. It assumes every site reaches the rate you enter. Many teams add sites above the calculated minimum as a buffer because some sites recruit nothing. Treat the result as a floor.

Is anything stored or sent?

No. The calculation runs in your browser and nothing is saved or transmitted.